May 27, 2008 (Day 121)

The Garage Came a-Tumblin’ Down

The second phase of demolition commenced today. Our demolition/excavators came back to destroy our single car garage, our front stoop, and a small accessory sidewalk on the south side of the front yard. They also dug a hole for the basement egress window that we are required to put in according to the building code (basement addition greater than 250 square feet).

The painters were hard at work on the second floor prepping the woodwork.

The installation crew from Countryside Cabinets arrived with the first load of cabinets for the main floor. They began installing cabinets in the pantry and the kitchen proper. Very exciting!